Study of Elementary Particle Physics at the LHC
    Task A – ATLAS
    The University of Michigan, Ann Arbor, MI 48105
    UM ATLAS Personnel name list
    1

    1 Introduction
    1.1 ATLAS at the University of Michigan
    The Michigan ATLAS group was formed in 1998 and rapidly developed into a world-class pro-
    gram. Our objectives for the program have been to accept major responsibilities and to play
    leading roles in many important areas within the ATLAS experiment. Among these assumed
    responsibilites we have designed and built large precision muon chambers, designed and built
    muon detector frond-end electronics, have led the US detector integration, pre-commissioning,
    and system tests at CERN both for H8 and X5 beam facilities and for detector preparations in
    building 184. We have contributed broadly to the muon software development including cali-
    bration algorithms and strategies for combining other detector data with muon tracking, GRID
    computing R&D, and collaborative tools development. We have assumed a new leadership role
    within the ATLAS physics community with the establishment of a muon calibration center in
    Ann Arbor. Michigan is one of the strongest institutes in the ATLAS experiment.
    This document presents a short perespective on the challenges and opportunities for ATLAS
    in the three years covered by this proposal. It then describes the university community we
    bring to this endeavor. the individuals working under the grant and the university facilities
    that are available. We then turn to the work accomplished in the past three year grant period
    by the University of Michigan ATLAS group. In the final sections we describe our plans and
    commitments to ATLAS and the support we require to accomplish these tasks.
    1.2 The ATLAS Experiment
    The ATLAS experiment is well into the commissioning phase with most detector components
    in place in the ATLAS cavern. Figure. 1 shows a picture of the last major component of the
    ATLAS endcap MDT, the A-side small wheen, as it was lowered into the cavern February 29,
    2008. This installation culminates the surface activities during which 240 muon chambers were
    built, instrumented, and tested. With the first collisions due at the LHC on July 1, 2008, our
    highest priority has to be the delivery of a top quality detector to ATLAS in the limited time
    remaining. The first of May 2008 has become the target date, our focus, and our challenge. The
    Michigan ATLAS group has fully committed and will continue to shoulder the primary load for
    ATLAS endcap muon detector commissioning and calibration.
    LHC is the first new energy frontier in a generation. The precise discoveries that will emerge
    from the LHC are unknown. In spite of these uncertainites, we must be ready to fully exploit
    the opportunity with top quality hardware and software. To do so requires that our attention
    remain directed toward detector commissioning, trigger, calibration/data preparation, software
    preparation for data acquision monitoring, event reconstruction, and for physics analysis. The
    software must be fully developed and mature if we are to understand what is present in the
    early data. We must also understand the SM physics landscape, as seen by ATLAS, prior to
    LHC collisions. Only when those foundations are built and well understood, can we address,
    with confidence, the most exciting and compelling issues in high energy physics:
    • The mystery of the origin of mass and the nature of electroweak symmetry breaking;
    • Whether supersymmetry existing, and at which energy scale such symmetry breaking?
    • Whether quarks and leptons have further structure at much smaller distance scale?
    • Whether nature indeed has extra spatial dimensions?
    • Whether a new interaction force, such as Technicolor, or a new gauge bosons exist?
    2

    Figure 1: A picture of the last major part of the muon MDT, the A-Side Small Wheel as it was
    lowered into the ATLAS cavern on Feb. 29, 2008.
    1.3 Michigan’s Commitments
    To extract answers to the above profound questions with LHC data, our group is committed
    to continued strong leadership in muon detection focusing on the physics potential for new
    discoveries with muon final states. Since we have established a large and highly experience team
    working on muon detector construction, commissioning, calibration, and database development
    which also possesses considerable expertise in computing and muon software, we propose to
    merge these activities into a team sufficient to tackle the task of muon “object” qualification.
    To optimize the quality of the “objects” we call muons, we must understand the detector, the
    signal muons, the signals we conclude are backgrounds, and calibrate the measurements so that
    the precision meets the specification required by the physics goals. These “objects” will be the
    input to our physics analysis and to the analysis of others. We will take this service role seriously
    including the need to document thoroughly algorithms and procedures developed.
    1.4 Overview of the group
    The Michigan ATLAS group comprises 25-30 people, including 6 faculty, 4 Research Scientists,
    3 postdoctoral fellows, 2 engineers, and 5 students. Four faculty, Chapman, Neal, Thun and
    Zhou are primarily working on the ATLAS Project. Chapman has been the project leader for
    the ATLAS muon front-end readout certification and for the design of the readout multiplexer
    (CSM), he led the endcap Big-Wheel commissioning at CERN; Neal has been the project leader
    for US ATLAS collaborative tools development, he also leads the ATLAS GRID computing effort
    at Michigan; Thun has been the muon detector construction project leader and the chamber
    constrution and quality assurance officer. He is leading the muon detector calibration effort for
    endcap muon system. Zhou is the US ATLAS MDT project leader, she led the US ATLAS
    endcap work at CERN for single chamber integration and certification. She continues to play
    3

    a leading role for ATLAS endcap commissioning. Two additional UM ATLAS faculty, Amidei
    and Qian are currently focusing on the Tevatron experiments (CDF and D0), and are currently
    in transition from Tevatron to LHC activity.
    Four Research Scientists, Diehl, Goldfarb, McKee, and Levin are supported by DoE base
    grant and are working full time on the ATLAS project. Levin led the US H8 test beam effort at
    CERN, the muon combined performance working group, and a muon data quality assessment
    activity in coordination with the calibration center at Michigan; McKee has been the endcap
    MDT production and certification database coordinator and is also the US ATLAS network R&D
    project leader. He continues to play a leading role at Michigan for ATLAS GRID computing
    and for high speed data transfers between the calibration center and CERN; Goldfarb served as
    the overall ATLAS muon software coordinator (2002 - 2007), and muon configuration database
    manager along with Tiesheng Dai (2008- now); Diehl manages the calibration center in Ann
    Arbor. He has also taken the responsibility for the development of programs for endcap muon
    calibration, particularly for handling the long tube wire sag RT function corrections.
    Three Michigan postdoctoral fellows are resident at CERN, Liu, Strandberg, and Ferretti.
    They are supported by base and non-base funds. Jianbei Liu is our liasion to the CERN gas
    group for all MDT chambers. He has been extremely valuable for maintaining safety and quality
    control over the gas system, making sure that chambers are appropriately outfitted with gas lines,
    maintained at the nominal 3 bar pressure, and flushed adequately prior to high voltage testing.
    Jonas Strandberg has contributed to the muon system running under control of the ATLAS
    daq. He has evaluated the on-line monitoring software and written an operations manual for
    shift personnel; Claudio Ferretti has contributed a broad spectrum of software and information
    handling software, both for data storage, retreival, and display.
    Our group has a very outstanding engineering staff, mechanical engineer Weaverdyck and
    electrical engineers, Ball and Dai. They are partially supported by our base program and par-
    tially supported by Project funds. These engineers represents one of the strongest assets we have
    provided the ATLAS experiment over the past years. They have handled many complex techni-
    cal issues. Weaverdyck is majority supported by another activity but serves as an outstanding
    reference for ATLAS mechanical designs. Dai remains in residence at CERN and continues to
    provide crucial technical support for commissioning, and detector calibration activities. Ball
    has assumed management of the Great Lakes Tier-II Center but continues to support the MDT
    front-end electronics to which he contributed much of the design. All three engineers have truly
    remarkable records over past 15-25 years in experimental high energy physics.
    2 MDT Commissioning
    2.1 Readout Chain and the Chamber Service Module (CSM)
    The readout for the muon MDT chambers is shown in Figure 9 and is composed of passive cards
    called hedgehog boards that deliver the high voltage at one end of the tubes and channel the
    readout signals from the opposite end to the front-end amplifier-shaper-digitizer cards at the
    other end. Digitized data from these cards is delivered to the on-chamber multiplexer (CSM)
    located nearby. The multiplexer assembles data from up to 18 front-end cards and sends it along
    an optical fiber to event builder modules (MROD) approximately 100 meters away. Michigan
    has contributed the design and programming of the on-chamber multiplexer and has coordinated
    the certification of the overall design. Our responsibilities extend to the full muon system since
    all MDT chambers are instrumented with the same US built front-end electronics.
    **Some text about continuing responsibilities for the front-end electronics.**
    4

    Figure 2: The Front-end Design of the MDT readout. Tubes connect through passive hedgehog
    cards to amplifier-shaper-discriminator chips (ASD) and then to time-digital-converter chips
    (AMT) on mezzanine cards that each process 24 tubes. Up to 18 mezzanine cards connect to a
    chamber-service-module (CSM), a time-division-multiplexer that sequences the data to muon-
    readout-driver modules (MROD) through a Gigabit optical fiber. Initialization of the multiplexer
    and mezzanine cards is provided through JTAG from an external-local-monitor-board (ELMB).
    Detector control, monitoring, and JTAG are all received by the ELMB from data sent on the
    CANbus.
    5

    2.2 Chamber Preparations, On-surface and In-cavern Testing
    2.2.1 On-surface Chamber Preparations
    Commissioning of the ATLAS MDT has proceeded in several major steps or phases first for
    the Big Wheel chambers and then for the Small Wheel chambers. In Phase-I single chambers
    were integrated and commissioned at CERN building 184 and later in building 191. In this step
    chambers were outfitted with electronics and monitoring devices followed by thorough testing.
    These single-chamber tests provide the primary chamber QA/QC parameters and database
    entry information. In Phase-II chambers and services including global alignment devices were
    added. In this phase, fully integrated and commissioned BW Sectors (32), SWs (2), as well
    as 16 individual EIL4 chambers were prepared and made ready for installation in the ATLAS
    cavern. Phase-II preparations started in October 2004 for BW sector assembly and completed
    in the December 2007 with the mounting of the SW chambers.
    During the many days of Phase II & III work, Michigan served as qualtiy control agents for
    much of the endcap muon effort, discovering problems and developing solutions. A partial list
    of issues is below.
    The Russian built EO chambers that mount directly to the cavern wall conform to the same
    design as US built chambers and use US/Japanese built electronics. For this reason these 192
    chambers have made use of the same procedures and daq stations provided by Michigan. In
    addition, the EO chamber component IDs and test results conform to the same format and are
    also entered into the commissioning database by Michigan. This completely unified approach
    to test software and information handling for all endcap chambers has led to a smooth and
    successful transfer of configuration data to the ATLAS data acquisition system. Responsibility
    for the configuration data for all of the MDT and CSC chambers is one of Michigan ongoing
    service responsibilities.
    • Discovery of Hedgehog board manutacturing faults (design of MECCA card tester)
    • Discovery of a mezzanine testing error (sorting and return of cards)
    • Application of Negative HV applied to tubes with high dark current
    • Location/repair/replacement of all defective electronic cards, T/B-sensors, cables, etc.
    • Discovery of a front-end chip fault (doubling of the readout multiplexer input and output
    speeds to sustain ATLAS specification)
    • Repair/disconnection of all physically damaged tubes
    • Repair of all broken fibers
    • Repair of all shorted tubes, disconnecting them from the HV line
    2.3 In-cavern Commissioning
    In Phase-III the Big Wheel and EIL4 chambers were tested in the cavern with the same small
    Michigan daq system used for surface testing five to eight chambers at time. The small daq
    station, high voltage, and low voltage supplies required moving between floors of the 9 story
    cavern. Testing was deemed absolutely essential after the sectors were trucked from the surface
    building, lowered into the cavern, formed into a single wheel, and mated to TGC wheels at front
    and back since repairs are essentially impossible now that the wheels are closed.
    6

    Later, as components became available, the Big Wheels were connected and tested with
    the final readout electronics. The Small Wheel chambers have been connected directly to the
    final electronics and tested in the ATLAS cavern. Commissioning with cosmic rays began in
    November 2007, first with the Big Wheel Side-C, later with Side-A, and finally with the two
    Small Wheels. In-pit commissioning will continue with cosmic-rays until collisions from the
    LHC become available. Michigan has led the Big Wheel commissioning effort and has continued
    in the Small Wheel effort providing test procedures, checklist, and daq stations developed for
    the Big Wheel work. All chamber characterizations and test results have been stored in the
    commissioning database loaded and managed by Michigan personnel.
    Over the past three years, the Michigan group has also played a leading role in the devel-
    opment of the software and database infrastructure essential to the commissioning of ATLAS
    Muon Spectrometer. The contributions have covered key aspects of the data chain, from detector
    running and monitoring, to data simulation, reconstruction and storage, to physics and perfor-
    mance studies. These efforts have been complementary to and supportive of our construction
    and installation tasks, and are essential for a thorough understanding of the detector. Steven
    Goldfarb coordinated the offline software development, Manuela Cirilli was the Muon Database
    Task Leader, and Dan Levin was a major contributor to the muon physics performance studies,
    as Muon Combined Performance Working Group Convener.
    In Phase-IV testing in the ATLAS cavern, the muon endcap commissioning team has ex-
    panded to include individuals from many institutions. Installation and operation of the MDT
    chambers in the ATLAS cavern has required immense coordination and many hours of work.
    All 432 chambers required connection to the services supplied by CERN but not attached to the
    detector elements by them. Chamber gas, low voltage, high voltage, slow controls, alignment
    readout, high speed fibers for readout, and trigger/timing control were all connected by the end-
    cap team. Michigan has been particularly central to most of these tasks. The challenge in all
    of these efforts is heightened by the very tight schedule requiring US team to be ready with the
    parts and manpower to step-in when a window opens. Handling the scale of these last minute
    tasks in the available time has only been possible with a significant on-site team. Michigan has
    provided the largest contingent of this team.
    2.4 Old Roles and New Roles
    With the broadening activities and increasing size of the operating detector, the Michigan team
    has focused on some new tasks and expanded their role in supporting tasks where they were
    already prime contributors. Jianbei Liu and student Aaron Ambruster have the primary respon-
    sibility for in-pit gas and HV issues, stopping leaks and certifying that the chambers operate
    successfully at the nominal HV. J. Chapman and Tiesheng Dai continue to examine the per-
    formance of the initialization and readout of the MDT, addressing any issue of reliability and
    functionality. Claudio Ferretti provides the code and primary off-line monitoring of the detec-
    tor’s operating state and environmental conditions. Manuela Cerilli, Jonas Strandberg, Andrew
    Eppig, J. Chapman, and Daniel Levin have all played key roles in the evaluation of data taken
    in runs since in-pit readout has commenced. Manuela and Jonas are responsible for the coor-
    dination of shifters and the DQMF developers along with the preparation of the Web log of
    run quality. Tiesheng Dai has assumed responsibility with Steven Goldfarb for the MDT and
    CSC configuration database, insuring that the database has correct entries for all of the nearly
    1/2 million channels of the detector. Each of the newly adopted tasks as well as the continuing
    responsibilities of the Michigan group are described in detail in sections below. To insure good
    coordination of Michigan activities internally and with others, Bing Zhou and J. Chapman have
    maintained a strong presence at CERN through the commissioning period.
    7

    2.5 Services
    2.5.1 Chamber Gas
    The MDT gas system must be leak tight to ATLAS specifications throughout the AAAAA
    tubelets, BBB gas bars, CCC lines, and DDD valves. The system must provide balanced flow of
    91% Argon 9% CO
    2
    at 3 bar to all 240 chambers such that 1 or 2 volumes are exchanged each
    24 hours. Gas services up to the connection to the chamber frames is provided and managed by
    CERN staff. Competing for the attention of this staff has been a major challenge for both the
    endcap MDT community and our competition.
    Gas tightness is a major factor in the MDT operation. Our success in maintaining the
    ATLAS specifications in this regard is illustrated in the plot of leak rate shown in Figure ??
    where the scale of the y-axis is the leak rate in multiples of the ATLAS specification, shown
    separately for the Big Wheel sectors and the Small Wheels, EE millibar/day. Quality control
    and repair work on the MDT gas system has primarily been a Michigan responsibility.
    2.5.2 Chamber High Voltage
    Providing High Voltage to the MDT in the ATLAS cavern is also a CERN responsibility up
    the sector or wheel edge. The contract for supplies is with CAEN (Italy). Delivery of these
    commercial supplies has been the most severe bottleneck inhibiting our cosmic-ray testing of
    the detector. Once the cables reach the edge of the detector, responsibiltiy shifts to the US teams,
    Michigan for the Big Wheels and Harvard/BU for the Small Wheels. Quality control clearly
    falls onto the US team for damage repair, leakage current testing for the cables, and chamber
    current draw at working voltage. In order to meet the aggressive schedule for installation while
    symultaneously being held back to permit access to other detectors, we have had to contribute
    to the connection and testing of the High Voltage power supplies from CAEN. A test fixture
    has been established at CERN to examine and certify High Voltage modules. Unfortunately,
    far too many, X%, of the units do not pass these initial tests. In-use failures are also far too
    common. In spite of the difficulties we have certified the wheels for operation within the ATLAS
    specifictions at the nominal chamber high voltage, 3080V. A plot of the leakage current is shown
    separately for a Big Wheel and Small Wheel chamber in Figure ??.
    2.5.3 DCS, LV, and Fibers
    Low Voltage services are also provided to the MDT by CERN, again under a contract with
    CAEN. Slow delivery of modules has also produced delays in testing with the final readout
    electronics. Cabling of the low voltage power up to the detector edge has also been provided by
    CERN. For the Big Wheel the commissioning has only been troubled by the shortage of final
    readout electronics and power supplies. The compressed commissioning schedule that resulted
    in the capture of the MDT Big Wheel between TGC wheels left us unable to discover and repair
    a few faults before they were inaccessible. This is particularly true for the fibers. Many of the
    Big Wheel trigger and readout fibers are radiation soft due to a material acquision problem at
    the supplier of the fibers. This sourcing problem has been acknowledged by the supplier and
    new radiation-hard fibers have been provided but access to install them is no longer possible.
    An early connectorization problem with the fibers was discovered and correction measures taken
    by the manufacturer. Any remaining connector separations of the fiber from the connectors will
    also be removed when the replacement fibers are installed at the first major shutdown. The
    Small Wheel has not experienced either problem.
    8

    Figure 3: Endcap Temperature Sensors Distribution.
    3 Data Collection, Monitoring, and Evaluation
    3.1 Detector Conditions Monitoring
    The health of the detector is critical both for avoidance of problems and for sustaining resolution
    by monitoring environmental conditions that impact detector operation. These conditions are
    examined on-line for exceptions to set alarms for shifters when limits are exceeded. In extreme
    situations detector components will automatically shutdown. On-line alarm systems are still
    under development and since Michigan is not responsbile for these systems, our descriptions will
    be confined to the off-line monitoring of the recorded measurements of temperature, voltage, B-
    field. The recorded values are maintained in a conditions database for association with data taken
    mfor muon tracking. One example displayed in Figure 3 exhibits the location of the temperature
    sensors in each of the stations of the endcap. From the sensors located at these positions, the
    temperature profile within the detector can be determined. It provides the necessary calibration
    information since the drift time depends on temperature.
    3.2 Muon Spectrometer Commissioning with Cosmic Rays
    A series of commissioning runs starting in late 2007 has enabled a evaluation of the detector
    characteristics from the basic drift tube functioning, to chamber resolution and calibration sta-
    bility. These runs have verified the detector connectivity, module identity, and proper database
    representation of the configuration and alignment of chambers. Overall performance and cali-
    bration characteristics have met expectations at this early stage of commissioning. These early
    tests are essential for the muon spectromter to be ready for physics on Day One of LHC running.
    9

    A few faults have been identified and repaired when the faulty component is accessible. Our
    contribution to these efforts is guided by expert knowledge of the chamber performance and
    electronics design, gained over the years of fabrication and particiaption in the H8 test beam.
    Cosmic ray commissioning milestone runs, commenced in the Autumn of 2007 and are con-
    tinuing through the Spring and summer of 2008. Two types of the commissioning runs are
    conducted: combined runs involving multiple ATLAS detector subsystems, and muon system
    only runs. These latter runs are intended to provide high statistics datasets wherein the data
    are collected in overnight periods with minimal human intervention. Data from these runs are
    very useful for MDT evaluations. While known problems exists in the chambers—e.g.: discon-
    nected tubes—these commissioning studies reveal problems hitherto unknown. It is critical that
    such faults be found quickly during the commissioning period—to allow some opportunity for
    remediation.
    The commissioning run program is analyzed by two complimentary means. The first is via
    the online data monitoring system which has been overseen by UM’s Manuela Cirilli. Jonas
    Strandberg, Andew Eppig, Aaron Armbruster and others from our group resident at CERN
    have been extensively involved in the data taking and analysis using this online monitoring
    framework. The online monitoring is an essential tool that will be used by shifters to insure
    data quality during actual LHC running. The commissiong runs provide the ideal environment
    to test this framework.
    3.2.1 Online Database and Data Quality Monitoring
    From 2005-2007, Manuela served, along with Joe Rothberg of the University of Washington, as
    the Muon Database Task Leader. In that role, she helped to plan and manage the development
    of a variety of databases specific to the Muon detectors, including certification, commissioning,
    configuration, and calibration, and reported directly to the Muon Software and ATLAS Online
    Database coordination. Manuela’s work typically involved much than project management, as
    several of the necessary databases either did not exist or were in an unsuitable state for long-
    term maintenance, when she started. She was thus responsible for designing developing tools
    and aiding in the creation of a well-integrated, coherent, and maintanable set of databases,
    accessible by a variety of online and offline interfaces.
    Some of Manuela’s specific efforts included: design of common barrel and endcap tables
    for the MDT certification database, definition of data schema and access in the commissioning
    database, adaption of interfaces to endcap commissioning data, and development of the MDT
    calibration database using the LCG COOL framework. It should be noted that the MDT
    calibration database was the first major implementation of a large conditions database, based on
    COOL, and interfaced to Athena. This work has expanded to support storage and retrieval of all
    conditions data, and will be a key component of the Muon Calibration Centers located at ATLAS
    Tier 2 Sites, such as Ann Arbor. Manuela’s proposed design of the database infrastructure for
    the Tier 2 sites, including data streaming and replication at CERN, has been tested and appears
    to satisfy the difficult 24-hour data turn-around constraints imposed for LHC data taking, an
    extremely important milestone in preparation for start up.
    3.2.2 Muon Performance
    In 2005, Dan Levin was asked to convene the Muon Combined Performance (MCP) working
    group, a part of the ATLAS Physics Coordination, steering all activities related to the identifi-
    cation and reconstruction of muons in ATLAS. For several years prior to his term, the MCP had
    been dormant, so Dan faced the additional challenge of identifying contributors and creating a
    10

    coherent project. During his term, Dan organized and presided over a large number of sessions
    through which significant contributions to the muon performance have been commissioned and
    presented. A solid body of contributors now regularly participates and is engaged in a number
    of specific studies of physics performance under realistic conditions. These studies are intended
    to quantify features of a large array of reconstruction algorithms, outline performance require-
    ments, establish standard metrics and specify the baseline reconstruction pathways to be used
    by ATLAS for LHC running. With each software release the MCP group evaluates the new
    performance with repect to previous releases and identifies potential faults in reconstruction
    that degrade muon sensitivy and momentum measurment. These studies are largely predicated
    upon physics processes and address the specific physics reach issues. Specific studies have ad-
    dressed misalignment impacts on Z and Higgs reconstruction, the effects of off-centered wires
    in drift tubes, evaluations of different inner detector tracking algorithms combined with muon
    spectrometer tracking.
    In the MCP Dan organized a sequence of Computing System Commissioning (CSC) Data
    Challenge based performance notes and appointed editors, and generally coordinated the ac-
    tivities of a widely dispersed community of physicists. He provided muon related support to
    external (non-Muon system experts) parties and actively encouraged participation of students
    in the activities of our group. This support includes documentation of the entire taxonomy of
    muon track reconstruction software in an ATLAS website: MuonRecoPedia. This site receives
    regular visits and updates from contributors. Dan also contributed to the authorship of the
    muon performance section of the new ATLAS Performance paper.
    3.2.3 Offline Software
    In 2007, Steve stepped down after completing two 2-year elected terms as the Muon Software
    Coordinator. Since beginning this task, the muon software effort evolved from a small group of
    somewhat independent tasks, to a large and coherent project, with more than 30 full-time devel-
    opers contributing to the software. Steve introduced structured project management, including
    detailed task breakdowns, personnel planning, and a relatively complete set of documentation.
    He also participated on the ATLAS Software and Muon Project Management Boards, as well
    as several steering groups, helping to drive the development in a direction that would best take
    advantage of the hard work we contributed to the construction of the detector.
    At the time of Steve’s departure, the software had successfully proven its ability not only to
    simulate physics in one of the most complex detectors ever constructed, but to reconstruct that
    data under realistic conditions, including the effects of detector imperfection, mis-alignment,
    mis-calibration, cavern background and event pile-up, with high precision and efficiency. Over
    the past few years, we have successfully used that same software to reconstruct cosmic data
    both in standalone mode and integrated with the rest of the ATLAS detector, as part of our
    detector commissioning effort. These capabilities were critical milestones in our preparation for
    LHC start up.
    3.2.4 Offline analysis
    For an alternative and immediate feedback on detector performance we also rely on standalone
    algorithms developed by Dan Levin, Tiesheng Dai, J. Chapman, and Andrew Eppig. This code
    currently is used to provide a detailed performance evaluation. The topics covered pertain to
    low-level and high-level performance diagnostics. The low level analyses focus on the fundamental
    and most critical aspects of MDT functioning, such as:
    • check that all enabled components report data reliably.
    11

    • determination of live, fully efficient tubes and inefficient tubes.
    • identification of isolated faulty tube and electronics channels
    • identification of the morphology of electronics related faults at various levels of chamber
    granularity. The morphology of a fault helps determine if the source is an isolated elec-
    tronics channel, a high voltage problem, a gas problem, or related to an ASD chip, a CSM
    module or MROD channel.
    • visual determination of the integrity of the TDC spectra.
    • chamber electronics noise frequency and hit occupancy.
    The high-level analysis extends beyond specific measurements of individual tube and elec-
    tronic channels and includes measurements of integrated chamber performance. The emphasis
    is to evaluate the uniformity of response of multiple chambers. This uniformity is determined
    here by a measurement of the maximum drift time distributions of all chambers with adequate
    hit statistics. A secondary of objective of the high level analysis is to evaluate the uniformity of
    track reconstruction by virtue of the hit residuals when a single time-to-space (RT) function is
    applied multiple chambers.
    A few examples from this analysis follow: We have prepared polar hit distribution plots
    where the chamber, multilayer, layer, and tube tube positions are shown approximately in their
    physical locations. This representation allows the pattern of hits to assist in the identification
    of the source specific failure modes. Tubes are symbolized by a rectangle color-coded for hit
    density. As an example: Figure 4 shows the hit distributions for the Endcap big Wheel Side
    A, Eta sector 5. In this run, half of the wheel was powered with high voltage. The annotation
    on the plot shows an inefficient chamber multlayer. This problem was linked to a gas flow fault
    and quickly remedied.
    As an example of a mid-level performance analysis, the maximum drfit time distributions for
    all chambers is measured. The maximum drift time is very sensitive to the gas mixture and to
    contaminants. So this measurement determines the gas homogeneity in the detector chambers.
    Figures 5 and 6 show the maximum drift time vs chamber and run number. The large scatter
    of the points is due the low statistics in many of the fits. However, the typical maximum drift
    time is near 700 ns, as expected.
    The success of the calibration depends on having a stable gas flow and gas conditions.
    Here we investigate the application of a single RT function obtained from the UM calibration
    chamber. This calibration is assessed from the track residuals. A typical endcap track is shown
    in Figure 7. These endcap chamber tracks are fairly oblique to the chamber multilayer plane
    and produce many tube hits. Residual distributions are found for those 15 chambers having
    adequate number of tracks: Figure 8, shows an example of these distributions with Gaussian fits
    around the peaks. The distribution of residuals suggests that the universal RT function yields
    reasonable track ”resolution” across all the endcap chambers. This initial attempt to apply a
    universal RT is very encouraging. Residual distributions for 15 chambers are fairly uniform and
    point to reasonable resolutions on the order of 100 microns.
    3.3 Ongoing Work
    A special focus of this work is to evaluate performance and calibrations of the MDT chambers.
    A single universal RT function, derived from the UM gas monitor shows encouraging results
    for endcap. Continuing commissioning runs will expand the number of chambers included in
    12

    Figure 4: Hit distribution in Endcap “Big Wheel”, Side A, Eta Section 5, in overnight cosmic ray
    Run 33182. Tube numbers increase outward radially. Counting of chamber Φ sector, Multilayers
    and layers increases counter clockwise.
    Figure 5: Maximum drift time for MDT wheel EMA vs chamber and run number.
    13

    Figure 6: Maximum drift time for MDT wheel EMC vs chamber and run number.
    these analysis. In a few months we expect that the entire muon precision spectrometer will be
    well-tested and calibrated for initial LHC running.
    3.4 Configuration Database
    4 Online Data Quality (DQ) Introduction
    UM has been a driving force in setting up an organization for fast feedback on the data quality
    during the cosmic-ray data taking in 2007 and 2008. The shifters are integral to the commis-
    sioning to verify that the MDT chambers are performing at the required level. The online DQ
    shifters collect fast information about status of Low Voltage (LV), High Voltage (HV), dead
    or noisy tubes and the quality of the data. This is then communicated to the muon operation
    shifter and to the hardware experts.
    5 Monitorig Tools
    The online DQ shifter can access the data from the Read Out Drivers (RODs) using the Online
    Histogram Display (OHD). The data is collected from the RODs, see Figure 9, and presented
    to the OHD with an application called GNAM. The histograms in GNAM contain chambers
    level distributions such as TDC and ADC spectra, hit multiplicity and error reports. There are
    also summary histograms showing the status of all chambers in a sector or a collection of four
    sectors.
    The number of histograms available are too numerous for the shifter to monitor and a large
    part of the initial DQ work has been to establish procedures and producing macros which can
    reliably catch problems with the data.
    The muon DQ shifters have pioneered the use of the Data Quality Monitoring Framework
    (DQMF). DQMF displays the histograms from GNAM and performs automatic tests for each
    chamber by comparing it to a set of reference distributions collected in previous runs. This is
    still in a development stage, but is forseen to be the main tool to be used by the DQ shifters in
    the future. Producing a set of reference histograms is problematic at this stage of the experiment
    as the operation of the detector is still in a state of flux due to, for example, changes in the
    trigger, in the readout configuration, in the LV and HV configuration, and so on. However,
    effective training of shifters can only be accomplished by having shifters actively using the tools
    and providing feedback to the developers.
    14

    Figure 7: Example of a tracks in EML5C13 chamber Run26464
    15

    Figure 8: Track residuals as seen in Sector 13 of Run 26464
    16

    Figure 9: Cartoon showing the muon calibration tools. For quick online monitoring of the data
    GNAM and DQMF are used, which accesses the data directly on the RODs. Analysis of the
    express stream data and the calibration ntuples allow for a more sophisticated monitoring of the
    data quality with a time delay of the order of a few days.
    6 Online DQ for Cosmic Data Taking
    The current DQ organization has been established since the fall of 2007 and has provided
    feedback during the last five cosmic data taking weeks (first in october of 2007 and last in
    march 2008). Since the start, shifters have been responsible for collecting information about the
    good runs and making it public on web pages such as the one shown in Figure 10. The runs are
    graded for quality by the shifter sent to the Tier0 for off-line processing and to the calibration
    centers for in-depth data quality monitoring and for determination of calibration constants.
    The sheer number of chambers to monitor proved challenging in the beginning and problems
    existed for days without being noticed. This spurred the development of more automatic tools
    to monitor the features of each run. The organization and working procedures have progressed
    to the point that all known problems in the latest data taking week (late february 2008) were
    spotted within hours and communicated to the detector experts.
    7 UM Contributions
    Manuela Cirilli is the current Muon Online DQ coordinator for Atlas and have been the driving
    force behind getting the data quality work started. She promoted efficient connections between
    the shifters and the hardware experts present at CERN and set up web pages which link infor-
    mation to the people stationed at the muon calibration centers. Jonas Strandberg is currently
    acting as the Muon Online DQ shift coordinator. For the graduate students stationed at CERN,
    DQ monitoring shifts provide an excellent introduction to the raw data coming from the Atlas
    muon chambers. All of the UM students at CERN have participated in the online DQ shift
    effort.
    Monitoring the data will be increasingly important as more and more chambers are being
    17

    Figure 10: The on-line DQ shifter grades the cosmics runs and provides run information and
    plots in a table of runs available on the web. The runs graded as good are then used at the
    calibration centers and are also sent to the Tier0 farm for offline processing.
    read out through the final readout chain. UM has had a leading role in the online data quality
    effort since the start of cosmic data taking and our expertize is vital to this effort. We foresee a
    continued role as the major institution responsible for the fast feedback from the DQ shifters.
    18

    Back to top