Calculating Total
    Power Requirements
    for Data Centers
    White Paper #3
    By Richard Sawyer

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    2
     
     
     
    Executive Summary
    Part of data center planning and design is to align the power and cooling requirements of
    the IT equipment with the capacity of infrastructure equipment to provide it. This paper
    presents methods for calculating power and cooling requirements and provides guidelines
    for determining the total electrical power capacity needed to support the data center,
    including IT equipment, cooling equipment, lighting, and power backup.

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    3
    Introduction
    With the adoption of scalable “pay as you grow” UPS architectures, its becoming easier to install these
    systems. It allows the data center manager to simply add modules as the needs of the data center grow.
    However, it is easy to lose sight of the future electrical needs of the data center or data room within a larger
    facility.
     
    Sizing the electrical service for a data center or data room requires an understanding of the amount of
    electricity required by the cooling system, the UPS system, and the critical IT loads. The power
    requirements of these elements may vary substantially from each other, but can be accurately estimated
    using simple rules once the power requirements of the planned IT load are determined. In addition to
    estimating the size of the electrical service, these elements can be used to estimate the power output
    capacity of a standby generator system, if one is required for the data center loads.
     
    Needs Assessment
    Any initiative to improve the capabilities of a data center environment, no matter the size or scale, must
    begin with a needs assessment. The needs assessment essentially establishes the availability needs of the
    business applications being processed by the IT equipment. A business process that is not time sensitive,
    or is batch process driven may dictate power and air conditioning for the load in an “N” configuration, with no
    internal redundancies to increase availability. More time sensitive sites may require a degree of redundancy
    in key component systems and have configurations of an “N+1” topology. Every key system element would
    have a redundant piece of equipment so that if one of the units fails, the system could still maintain its
    function for the IT critical load. The most critical data center applications requiring total availability (7x24)
    would have a 2N topology where critical systems would be completely redundant. One critical system could
    fail, but another would maintain operational loads. This also provides for a degree of concurrent
    maintainability whereby maintenance could be performed on one system while another supplies the load.
    For more information on the different types of system configurations see APC White Paper #75, “Comparing
    UPS System Design Configurations”.
     
    No matter what the actual UPS system design configuration is (N, N+1, 2N), the core issue of providing
    sufficient power to the critical load and keeping it cool is the same, and must be carefully addressed.
    Underestimating the required capacity may result in future power disruptions when forced to increase
    capacity, and over estimating leads to excessive initial installation costs and higher ongoing maintenance
    expenses.
     

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    4
    Determining the Electrical Power Capacity Needed to
    Support a Data Center
    Most data centers are part of a larger building. The steps in determining the electrical capacity described
    below will assist in estimating the capacity required for that portion of the building dedicated to the data
    center or data room. The difference between the steady state power and the peak power is important when
    calculating power capacity requirements and is noted throughout this paper. For more information on why
    power variations exist read APC White Paper #43, “Dynamic Power Variations in Data Centers and Network
    Rooms”. For installations where critical components like air conditioning, chillers, or standby generators are
    shared and used to supply other loads beyond the data center, the sizing of the system requires a more
    complete and complex analysis by a consulting engineer.
     
    Figure 1 illustrates a typical breakdown of how the electrical capacity is divided among the various loads in a
    data center. This breakdown assumes 5,000 ft
    2
    , (465 m
    2
    ) data center with an initial steady state critical load
    of 50kW, plus a future steady state load of 50kW. The cooling system is assumed to be direct expansion
    (DX) and the utility voltage is 480 volts AC.
     
    Figure 1
    – Breakdown of data center electrical requirements
    DX cooling system
    50%
    Lighting
    3%
    UPS ineffiency /
    battery charging
    11%
    Critical loads
    36%
     
    Critical loads
    A proper planning exercise in developing a data center, from a single rack sized environment to a full scale
    data center begins with determining the size of the critical load that must be served and protected. The
    critical load is all of the IT hardware components that make up the IT business architecture: servers,
    routers, computers, storage devices, telecommunications equipment, etc., as well as the security systems,
    fire and monitoring systems that protect them. This process begins with a list of all such devices, with their
    nameplate power rating, their voltage requirements, and whether they are single phase or three phase
    devices. The nameplate information must then be adjusted to reflect the true anticipated load. The
    nameplate power requirements are the worst­case power consumption numbers required by Underwriter’s

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    5
    Laboratory and in almost all cases, are well above the expected operating power level. Studies conducted
    by reputable consulting engineering firms and power supply manufacturers indicate that the nameplate rating
    of most IT devices is well in excess of the actual running load by a factor of at least 33%. The U.S. National
    Electrical Code (NEC) and similar worldwide regulatory bodies also recognize this fact and allow electrical
    system planners to add up nameplate data for anticipated loads and multiply by a diversity factor,
    anticipating that not all devices are running at full load 100% of the time. Alternatively, an advanced sizing
    calculator may be used such as the one found at the website below. Calculators such as this one gather
    power consumption data from a wide range of manufactures and further specify various equipment
    configurations.
     
    www.apcc.com / template / size / apc / index.cfm
     
     
    At this site an IT professional can configure a representative rack’s worth of servers based on “brand­name”
    ingredients. This tool works behind the scenes to add up the known power requirements of each component
    within a given server’s configuration. For example, when a user specifies a server, they will also be asked to
    record the quantity of CPU and other details within the box. Given the user’s inputs, the UPS Selector will
    calculate the total power required for the rack. (The power will be stated in volt amps or VA) Also included
    in the tool are important facts about the manufacturers intended input voltage and power plug.
     
    With the list of anticipated components comprising the critical load, the base load can be established by
    using a sizing calculator. For IT equipment unlisted in calculators as well as the power requirement for fire,
    security and monitoring systems, the following process should be used:
     
    A. Add up the nameplate power of the anticipated loads. If the wattage is not listed on the device, it
    can be determined by multiplying the current (amps) by the voltage of the device to get the VA,
    which approximates the amount of watts the device will consume.
     
    B. Multiply the anticipated VA number by 0.67 to estimate the actual power, in watts, that the critical
    load will represent.
     
    C. Divide the number by 1000 to establish the Kilowatt (kW) load level of the anticipated critical load.
     
    Future loads
    Data Center loads are not static. Once built or established, the IT equipment will be under an almost
    constant state of change during the lifetime of the data center. IT “refreshes” will, at a minimum, have a 3
    year cycle where new, more powerful or efficient devices will be installed with, or replace the devices on the
    initial planning list. A realistic assessment of the scope and timing of future changes and upgrades should
    be developed by the IT organization to allow proper planning for the initial determination of power
    requirements. The “downstream” elements of the electrical power and distribution system can be scaled, or
    adjusted to known loads and future loading (See APC White Paper #37, “Avoiding Costs from Oversizing
    Data Center and Network Room Infrastructure”), but the electrical power service supplying the NCPI

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    6
    components has to be sufficiently sized to carry the known load at start­up and future loads, or provision has
    to be made for installing additional capacity without incurring excessive downtime that would adversely affect
    the availability expected by the IT customer.
     
    Once an estimate is made for the amount of future loading, it is added to the base loading information
    developed above to establish the electrical critical load number in kW.
     
    UPS loads
    Assuming that the availability determination in the needs assessment, explained above, requires the
    inclusion of UPS power (in almost all cases this is true), the total electrical load power must include a factor
    for the inefficiency of the UPS system as well as the additional power required for battery charging.
     
    UPS efficiency varies between product models and varies dramatically depending on the loading of the UPS.
    UPS are rarely run at the operating points where their advertised efficiency is provided. A realistic and
    sufficiently accurate value for UPS efficiency in a typical installation is 88%.
     
    Battery charging is a significant but intermittent power consumer. Under normal operation with a charged
    battery the battery charging load is negligible. However, when a battery has been partially or completely
    discharged the battery charging power can be on the order of 20% of the rated UPS load. Although this load
    only rarely occurs, the generator and service entrance must be sized for this load.
     
    Lighting loads
    Lighting loads account for all the lighting in the data center portion of the building and are a function of the
    data center floor area. A good rule of thumb for this type of load is 2 watts per square foot or 21.5 watts per
    square meter.
     
    Cooling loads
    Refer to APC White Paper #25, “Calculating Total Cooling Requirements for Data Centers”, for a detailed
    discussion of heat loads in data center environments. The paper provides tables to help calculate the
    cooling required for the heat generated by the IT equipment. It also allows the planner to establish the
    amount of cooling required to support a planned critical load. Cooling systems vary widely in efficiency but
    can be broken down into chilled water systems and direct expansion systems. Chilled water systems are
    generally more efficient and a rule of thumb for power consumption is 70% of the total peak load being
    supported. Direct expansion systems require about 100% of the total peak load being supported. Note that
    cooling loads have startup peak loads that exceed the steady state values which are accounted for in this
    calculation. Table 1 of this paper estimates the electrical power requirement of the cooling system using
    these rules. This will help establish the size of the electrical distribution system required to support the entire
    data center.
     
     
     

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    7
    Sizing the electrical power system
    Two important numbers have been determined that will assist in estimating the size of the electrical system
    that will power the data center environment: the Total Critical Load and the Total Cooling Load. In general,
    the electrical supply must be large enough to support the sum of these two numbers, plus the related data
    center lighting loads.
     
    The steady­state power consumption of the loads within a data center establishes the power consumption for
    purposes of determining electrical costs. However, the Electrical Service and the Generator power sources
    that provide power to the data center cannot be sized to the steady state values. These sources must be
    sized to the peak power consumption of the loads, plus any derating or oversizing margins required by code
    or standard engineering practice. In practice, this causes the electrical service and generator sizing to be
    substantially larger than might be expected, as will be illustrated in the next section.
     
    Final Electrical Capacity Computation
    Once the total electrical capacity is estimated in Kilowatts from the process described above, two critical
    determinations can be made: the first is an estimate of the electrical service needed to supply the data
    center, and the second is the size of any standby power generator capacity that may be needed to achieve
    the desired availability.
     
    Sizing of the Electrical Service
    The electrical service can be calculated as follows:
     
    1. Take the total electrical capacity required in Kilowatts and multiply by 125% to meet the requirements
    of the National Electrical Code and similar regulatory bodies.
    2. Determine the three phase AC voltage of the service entrance to be supplied by the utility company.
    Typically this is 480 Volts AC in the United States and 230 Volts AC in most other parts of the world.
    3. Use the following formula to determine the electrical service size to supply the data center, in Amps:
     
    Amps = (kW x1000) / (Volts x 1.73)
     
    This provides an estimate of the electrical service capacity required to support the critical load, cooling, and
    the building functions for a data center. Using the assumptions of Figure1, Figure 2 emphasizes the
    important distinction between rated (peak) power and steady state power by comparing the electrical service
    requirements for both. It must be noted that this is only an estimate, and that the final determination of the
    service size is highly dependent on accurate site specific information. It is strongly recommended that the
    services of a qualified professional consulting engineer be retained to verify the initial estimate and develop
    the final data center electrical supply design. Table 1, located at the end of the paper, can be used as a
    worksheet that assists in summarizing the discussion above.
     

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    8
    Figure 2
    – Rated vs. steady­state electrical service power for a typical 100kW critical load.
    Electrical service rating is almost 4X the steady state critical load value
     
     
     
    Sizing of Generator Standby Power Systems
    Once the size of the electrical service has been determined, consideration can be given to sizing of an
    appropriate standby power generator, which will provide power in the event of a utility failure and increase
    the availability of the data center. A typical generator installation is illustrated in Figure 3 below:
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
    Critical Load
    Critical Load
    UPS Load
    UPS Load
    Air Conditioner Load
    Air Conditioner Load
    0
    50
    100
    150
    200
    250
    300
    350
    400
    Electric Service Rated Electric Serivce Steady State
    kW
    Critical Load
    Lighting Load
    UPS Load
    Air Conditioner Load
    Electrial Service Derating

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    9
     
    Figure 3
    – Typical generator system
    Utility
    Generator
    Transfer Switch
    Emergency Bus
    UPS
    Mechanical Loads
    (Air Conditioning)
    Other Loads
    (Lighting, etc.)
    Critical IT Load
     
     
    The first thing to note on the diagram above is the assumption that the data center is the only load, and that
    it is to be fully protected by standby power. The “utility” supply may be only a part of a standard commercial
    electrical distribution system, so this diagram would be part of a subset of a much larger electrical system.
    This subset is the data center portion that supplies the critical IT loads.
     
    To estimate the size of the generator required for the critical loads, use the calculation at the bottom of Table
    1. However, there has to be consideration of the electrical characteristics of the loads to be attached to the
    generator through the transfer switch. Mechanical loads, for example, require high starting currents and
    impose harmonic currents that pose problems to a generator’s ability to supply the power needed. The UPS
    itself may contribute to this problem if it does not operate at a high input power factor, and may cause
    generator failure if it imposes a leading power factor on the generator.
     
    The selection of a UPS system with operating characteristics favorable to reliable generator operation is an
    extensive discussion, not covered in this white paper. It is sufficient to note that the UPS must be chosen
    carefully to achieve end­to­end reliability. A UPS system that exhibits highly capacitive characteristics under
    low load conditions is to be avoided. Certain UPS topologies, such as the delta conversion, are ideal for
    generator supplied systems and will not produce the undesirable operating characteristics of traditional
    double conversion systems with input filter capacitors. This choice alone in the selection of the UPS can
    influence the required generator size greatly, frequently by a factor of 3 (the generator would have to be 1.75

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    10
    to 3 times larger for a typical double conversion UPS than a Delta Conversion UPS). As in the case of
    electrical service power, Figure 4 emphasizes the important distinction between rated (peak) power and
    steady state power by comparing the electrical generator requirements for both.
     
    When selecting a generator, base the choice on the kW rating of the generator for purposes of simplicity, but
    be aware that generators are designed to operate loads at a lower power factor than 1.0, typically 0.8. This
    means that the current and voltage will be slightly out of phase and that the generator must withstand that
    difference. A 1000 kW generator, designed to operate loads having a power factor of 0.8 will be rated at
    1200 kVA. Do not confuse the kVA rating with the true power capacity of the generator, which is always in
    kW. For more information on power factor see APC White Paper #15, “Watts and Volt­Amps: Powerful
    Confusion”.
     
    Figure 4
    – Rated vs. Steady­State electrical generator power for a typical 100KW critical load.
    Electrical service rating is over 4X the steady state critical load value
     
     
    Critical Load
    Critical Load
    UPS Load
    UPS Load
    Air Conditioner Load
    Air Conditioner Load
    0
    50
    100
    150
    200
    250
    300
    350
    400
    450
    Generator Rated Generator Steady State
    kW
    Critical Load
    Lighting Load
    UPS Load
    Air Conditioner Load
    Oversizing due to Critical loads
    Oversizing due to Cooling loads

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    11
    Table 1
    – Data center power requirement estimate calculation worksheet
     
    Item
    Data Required
    Calculation
    Subtotal kW
    Power Requirement – Electrical
    Critical load­ sizing calculator
    value from APC website
    Rating of each IT device
    ( Calculator total in VA x 0.67 ) /
    1000
     
    # 1 ____________kW
    For equipment not listed in
    the sizing calculator, critical
    load – nameplate
    Subtotal VA (include fire,
    security and monitoring systems)
    ( Subtotal VA x 0.67 ) / 1000
     
     
    # 2 ____________kW
    Future loads
    VA of nameplate of each
    anticipated IT device
    [ (Add VA rating of future
    devices) x 0.67 ] / 1000
     
    # 3 ____________kW
    Peak power draw due to
    variation in critical loads
    Total steady state critical load
    power draw
    ( # 1 + # 2 + # 3 ) x 1.05
     
    # 4 ____________kW
    UPS inefficiency and battery
    charging
    Actual Load + Future Loads
    (In kW)
    ( # 1 + # 2 + # 3 ) x 0.32
     
    # 5 ____________kW
    Lighting
    Total floor area associated with
    the data center
    0.002 x floor area (sq ft), or
    0.0215 x floor area (sq m)
     
    # 6 ____________kW
    Total power to support
    electrical demands
    Total from # 4, # 5 and # 6
    above
    # 4 + # 5 + # 6
     
     
    # 7 ____________kW
    Power Requirement ­ Cooling
     
    Total power to support
    cooling demands
    Total from # 7 above
    For Chiller systems # 7 x 0.7
    For DX systems # 7 x 1.0
     
     
    # 8 ____________kW
    Total Power Requirement
     
    Total power to support
    electrical and cooling
    demands
    Total from # 7 and # 8 above # 7 + # 8
     
     
    # 9 ____________kW
    Size of Electrical Service Estimate
    Requirements to meet NEC
    and other regulators
    Total from # 9 above # 9 x 1.25
     
    # 10 ____________kW
    Three phase AC voltage
    provided at service entrance
    AC voltage
     
    # 11 ___________VAC
    Electrical service required
    from utility company in
    Amps
    Total from # 10 and AC voltage
    in # 11
    ( # 10 x 1000 ) / ( # 11 x 1.73 )
     
     
    _______________Amps
     
    Size of Standby Generator Estimate (If applicable)
    Critical loads requiring
    generator back up
    Total from # 7 above # 7 x 1.3*
     
    # 12 ___________kW
    Cooling loads requiring
    generator back up
    Total from # 8 above # 8 x 1.5
     
    # 13 ___________kW
    Size of generator needed Total from # 12 and # 13 above
     
    # 12 + # 13
     
     
    _______________kW
     
     
    *WARNING: The 1.3 variable applies to fully power factor corrected UPS. A 3.0 multiplier must be used when using
    traditional double conversion UPS with input harmonic filters.
     

    2004 American Power Conversion. All rights reserved. No part of this publication may be used, reproduced, photocopied, transmitted, or
    stored in any retrieval system of any nature, without the written permission of the copyright owner.
    www.apc.com
    Rev 2004­0
     
     
    12
    Conclusions
    Assessing the electrical power required to support and cool the critical loads within the data center is
    essential in planning for the development of a facility that will meet the end user’s availability expectations.
    By employing the process described above, a reasonable estimate of the power requirements can be made.
    This will help specify the size of the Network­Critical Physical Infrastructure components that will achieve the
    availability determined by the needs assessment. Once the sizing determination is made, conceptual and
    detailed planning can go forward with the assistance of a competent NCPI systems supplier or, in the case of
    larger scale data centers, a consulting engineer. Cost estimation can then be made based on the size and
    reliability configuration determined from the power needs assessment process described above.
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
    About the Author:
    Richard L. Sawyer
    is a Sr. Systems Application Engineer for APC. He has 25 years of experience in large
    scale data center construction and operations for Fortune 100 companies. He is on the Board of Directors,
    AFCOM.

    Back to top