|   | - Task A: ATLAS
- LHC & ATLAS Schedule
-
- Phase II: Surface Assembly of BW & SW
- Phase III: Installation of BW/SW in Pit
- UM ATLAS Project Tasks
- Remarks on FY2004 UM ATLAS Project
- Atlas Hall Status
- Slide 9
- Slide 10
- Movie: UM ATLAS Activities at CERN
- ATLAS Muon Project Phase I Chamber Integration and Test
- Pilot Work at Ann Arbor
- The UM Activities Moved to CERN in 2004
- Infrastructure in CERN Building 184
- Task and Major Procedures
- What does it mean to integrate and test one MDT chamber?
- Chamber Integration and Test (CIT) Status In Building 184
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
- Summary
- ATLAS Production and Commissioning Databases Development and Maintenance
- Database Software
- UM ATLAS Database System
- US ATLAS Phase I Commissioning Info
- Commissioning DB on Web
- Ongoing and Future
-
- Slide 33
- Slide 34
- Slide 35
- Slide 36
- Slide 37
- Slide 38
- Slide 39
- End Cap Chamber Sagitta vs Alignment
- Slide 41
- Slide 42
- Slide 43
- Slide 44
- Slide 45
- Slide 46
- MDT Electronics, X5, & H8 Work by UoM
- Leading Issues Ahead
- Focus of Individuals
- MDT-R/O Architecture
- The UoM Device, CSM
- Motherboard Status
- AMT Fault in Pair Mode
- Fault in Pair Mode (Cont.)
- Life without Pair Mode
- Avoiding Overruns at 80MHz
- Previous Work
- X5 Tests (Setup)
- X5 Tests (Spectrum)
- X5 Tests (m or g)
- X5 Tests (Efficiency)
- X5 Tests (Autocalibration)
- X5 Tests (Time Walk)
- Radiation Sensitivity Tests
- Radiation Test Equipment
- Total Ionizing Dose
- SEU Observations
- SEU Expectations
- CSM production
- Phases of Commissioning
- Commissioning Phase I
- Mobile Electronics Test Cart
- Electronics Tests
- Electronics Requirements
- Phase II Operation Details
- Dictionary
- Dictionary (continued)
- UM ATLAS Computing and Analysis Activities: 2003/2004
- University of Michigan Activities in ATLAS Computing and Analysis
- Highlights
- Muon Software Development
- Muon Software Coordination
- Muon Software Coordination
- Chamber Certification Software
- Slide 85
- Michigan Network and Grid Efforts in Support of ATLAS
- Network/Grid Related Activities at UM
- Network Leadership
- Proposals to Support our Efforts
- ATLAS Multi-Grid Production for DC2
- Data Challenge 2 at Michigan
- Studies of Hyperon Polarization at the LHC
- Λb Polarization Studies
- Slide 94
- Slide 95
- First Implementation of EvtGen Package in ATLAS with Polarization
- EvtGen Overview
- Decay of Polarized Lb in EvtGen
- Slide 99
- Report on UM ATLAS Collaborative Tool Activities
- Scope of Activities
- Recordings of ATLAS Events and Development of Web Capture Technology
- Ann Arbor – Geneva
- UMATLAS and Tier-2 Planning
- Intent to Compete for Tier-2 Status
- Summary of UM ATLAS Project
- Summary of UM ATLAS Project (2)
- Slide 108
- ATLAS Computing Timeline
- Major UM ATLAS Tasks in FY2005
- Transition from Construction to M&O
- Motivation for Funding Request
|