1. Funds
  2. Schedule
  3. Offsite
  4. Graph
  5. People
  6. Unfinished
  7. Finished
  8. CSCoffsite
  9. CSCcern
  10. Test Stations
  11. 184equip
  12. CSCequip
  13. Elec Equip
  14. Align Equip
  15. 180BWequip
  16. 191SWequip
  17. BWloadtest
  18. SWload
  19. SWtest
  20. Comwork
  21. Base Only
  22. Residency

  A B C D E F G H I J K L M N O P Q R S T U V
1                                              
2                                              
3 Activity BaseM&O M&O BaseProj Project BaseTot Proj/M&O Total                              
4                                              
5 Prepare 0 674 258 413 258 1087 1344                              
6 Mount 221 89 30 647 251 736 987                              
7 Fractions 9.5% 32.7% 12.4% 45.5%     2331                              
8 Travel 145 446 190 620 335 1066                                
9 Equipment   653       653                                
10                                              
11 Total   1862   1679 844 3542                                
12                                              
13                                              
14   Rollup K$ for years 2004/2005                                      
15 Activity Base M&O Project Total                                    
16 AtSites 258   683 941                                    
17 Mount 251 647 89 987                                    
18 Verify   674 413 1087                                    
19 Equipment   653   653                                    
20 Travel 73 349 484 906                                    
21                                              
22 Totals 582 2323 1669 4574                                    
23                                              
24                                              
25                                              
26     Project Totals                                    
27   WBS Categories Total Hrs Tech Hrs Engr Hrs PhD Hrs Total k$                              
28 1.5.4.7 CSC Install   1070 742 283 44 36                              
29 1.5.7.11.1 SW Above   570 439 44 88 17                              
30 1.5.7.11.2 BW Above   12063 9038 2738 287 376   Total Project Funds (K$)                      
31 1.5.7.11.3 EIL4 Pit   1598 1162 145 291 51   480                          
32 1.5.12.5.1.1 Alignment System 0 0 0 0 0   Total M&O Funds (K$)                      
33                   1206                          
34 3.5.1.1.1.2.1 MDT Phase I Mech 7226 5343 1883   228                              
35 3.5.1.1.1.2.2 Ditto, Electrical 5734 4236 1498   181                              
36                                              
37 3.5.1.1.1.3.1 MDT Phase II Mech 5546 4266 427 853 168                              
38 3.5.1.1.1.3.2 Ditto, Electrical 3522 2710 271 542 107       Total hours from Schedule = 53865                
39                                              
40 3.5.2.1.1.2.1 CSC Phase I Mech 1401 940 461   49                              
41 3.5.2.1.1.2.2 Ditto Electrical   1226 822 404   42                              
42                                              
43 3.5.2.1.1.3.1 CSC Phase II Mech 637 490 49 98 19                              
44 3.5.2.1.1.3.2 Ditto Electrical   750 577 58 115 23       All Years                      
45                       Total Hrs Tech Hrs Engr Hrs PhD Hrs                
46 3.5.3.1.2 Alignment Phase I 2682 1989 692   84       61212 44706 12618 3888                
47 3.5.3.1.3 Alignment Phase II 9988 7632 785 1571 305                              
48                                              
49   Totals   35409 25158 9485 766 21506 16251 2800 2455 4297 3297 333 667 $556,361 $96,990 $0 $609,611 $395,975 $85,938    
50       FY 2004       FY 2005       FY2006       2004 2005 2006 2004 2005 2006    
51   WBS Categories Total Hrs Tech Hrs Engr Hrs PhD Hrs Total Hrs Tech Hrs Engr Hrs PhD Hrs Total Hrs Tech Hrs Engr Hrs PhD Hrs Equipment     Travel        
52 1.5.4.7 CSC Install   785 523 262 0 143 110 11 22 143 110 11 22       $14,689 $2,669 $2,946    
53 1.5.7.11.1 SW Above   0 0 0 0 285 219 22 44 285 219 22 44       $0 $5,338 $5,891    
54 1.5.7.11.2 BW Above   8853 6613 2162 78 3210 2425 576 209 0 0 0 0       $165,765 $60,097 $0    
55 1.5.7.11.3 EIL4 Pit   1065 775 97 194 533 387 48 97 0 0 0 0       $19,945 $9,972 $0    
56 1.5.12.5.1.1 Alignment System 0 0 0 0 0 0 0 0 0 0 0 0       $0 $0 $0    
57                                              
58 3.5.1.1.1.1.1 MDT Station Design 3360 2240 1120 0                 $383,761 $96,990 $0 $62,911 $0 $0 0.666667  
59 3.5.1.1.1.2.1 MDT Station Setup 1680 1120 560 0                                
60 3.5.1.1.2.1.1 MDT Phase I Mech 5912 4372 1541   1314 971 342   0 0 0         $110,694 $24,599 $0    
61 3.5.1.1.2.2.1 Ditto, Electrical 4691 3466 1225   1042 770 272   0 0 0         $87,836 $19,519 $0    
62                                              
63 3.5.1.1.3.1.1 MDT Phase II Mech 924 711 71 142 3697 2844 284 569 924 711 71 142       $17,307 $69,228 $19,102    
64 3.5.1.1.3.2.1 Ditto, Electrical 587 452 45 90 2348 1806 181 361 587 452 45 90       $10,992 $43,968 $12,132    
65                                              
66 3.5.2.1.1.1.1 CSC Stn Design BNL 576 192 384 0                 $131,000 $0 $0 $10,785 $0 $0 0.8  
67 3.5.2.1.1.1.2 CSC Stn Design UCI 144 48 96 0                                
68 3.5.2.1.1.2.1 CSC Stn Setup BNL 576 192 384 0                             0.8  
69 3.5.2.1.1.2.2 CSC Stn Setup UCI 144 48 96 0                                
70                                              
71 3.5.2.1.2.1.1 CSC Phase I Mech BNL 654 438 215 0 467 313 154   0 0 0         $12,242 $8,744 $0 0.8  
72 3.5.2.1.2.1.2 CSC Phase I Mech UCI 163 110 54 0 117 78 38                          
73 3.5.2.1.2.2.1 Ditto Electrical BNL 572 384 188   409 274 135   0 0 0         $10,711 $7,651 $0 0.8  
74 3.5.2.1.2.2.2 Ditto Electrical UCI 143 96 47   102 69 34                          
75                                              
76 3.5.2.1.3.1.1 CSC Phase II Mech BNL 0 0 0 0 255 196 20 39 255 196 20 39       $0 $4,773 $5,268 0.8  
77 3.5.2.1.3.1.2 CSC Phase II Mech UCI 0       64 49 5 10 64 49 5 10                
78 3.5.2.1.3.2.1 Ditto Electrical BNL 0 0 0 0 300 231 23 46 300 231 23 46       $0 $5,614 $6,196 0.8  
79 3.5.2.1.3.2.1 Ditto Electrical UCI 0       75 58 6 12 75 58 6 12                
80                                              
81 3.5.3.1.1.1.1. Alignment Design 720 480 240 0                 $41,600 $0 $0 $13,481 $0 $0    
82 3.5.3.1.1.2.1. Alignment Setup 0                                      
83 3.5.3.1.2.1 Alignment Phase I 2194 1628 567   488 362 126   0 0 0         $41,085 $9,130 $0    
84 3.5.3.1.3.1 Alignment Phase II 1665 1272 131 262 6659 5088 524 1047 1665 1272 131 262       $31,168 $124,673 $34,402    
85                                              
86 FTE     20.2 14.4 5.4 0.4 12.3 9.3 1.6 1.4 2.5 1.9 0.2 0.4                
87                                              
88 3.2 FTE from institution staff travel or residency at CERN with travel cost for 2004/2005 of   $1,065,653                            
89 Pro rated travel   $662,982       $402,671       $88,804                      
90 Equipment     $556,361       $96,990       $50,000.00                      
91                                              
92 Rough cost Labor   $1,369,798 $754,749 $569,079 $45,970 $802,848 $487,525 $168,020 $147,303 $158,920 $98,910 $20,003 $40,007                
93                                              
94 Year totals     $2,589,141       $1,302,509       $297,724                      

Back to top


  A B C D E F G H I J K L M N O P
1     M&O Planning numbers for Endcap muon certification, installation, and commissioning              
2                                  
3   Design & Assembly of Test Fixtures for Building 184                      
4                                  
5 Steps Institution DateStart Stations Days/stn #Stations Weeks Technicians Engineer EndDate   Total hrs Tech hrs Eng hrs      
6   All MDT 1-Sep-03 5 30 1 30.0 2 1 15-Feb-04   3600 2400 1200      
7                                  
8   Design & Assembly of Test Fixtures for CSC at CERN                      
9                                  
10 Steps Institution DateStart Stations Days/stn #Stations Weeks Technicians Engineer EndDate   Total hrs Tech hrs Eng hrs      
11   All MDT 1-Sep-03 1 30 1 6.0 1 2 15-Feb-04   720 240 480      
12                                  
13   Design & Assembly of Test Fixtures for Alignment at CERN                      
14                                  
15 Steps Institution DateStart Stations Days/stn #Stations Weeks Technicians Engineer EndDate   Total hrs Tech hrs Eng hrs      
16   All MDT 1-Sep-03 1 30 1 6.0 2 1 15-Feb-04   720 480 240      
17                                  
18   Design & Assembly of Test Fixtures for Building 180                      
19                                  
20 Steps Institution DateStart Stations Days/stn #Stations Weeks Technicians Engineer EndDate   Total hrs Tech hrs Eng hrs      
21   All MDT 1-Sep-03 1 30 1 6.0 2 1 15-Feb-04   720 480 240      
22                                  
23   Design & Assembly of Test Fixtures for Building 191                      
24                                  
25 Steps Institution DateStart Stations Days/stn #Stations Weeks Technicians Engineer EndDate   Total hrs Tech hrs Eng hrs      
26   All MDT 1-Sep-03 1 30 1 6.0 2 1 15-Feb-04   720 480 240      
27                                  
28   Integration - BW Chamber Qualification with Electronics - to complete & test first N sectors N= 8            
29                     Total Chambers of each type        
30 Steps Institution DateStart Chambers Days/chm #Stations Weeks Technicians Engineer EndDate   BW SW EIL4 EE    
31 0.0 UM 21-Feb-04 20 8.0 3 10.6 6 2 24-Mar-04   80 0 0 23    
32 0.0 UW 18-Jan-04 16 8.0 2 12.7 4 2 13-Mar-04   64 0 16 28    
33 0.0 BMC 23-Apr-04 4 3.6 2 1.5 5 1 09-May-04   16 64 0 13    
34   B..Wheel 21-Feb-04       24.8 15 5                
35                         UW Finished 43      
36   Integration - Remaining Chamber Qualification with Electronics - to complete remainder of chambers     UW Un-Fin 37      
37                         Total 80      
38   Institution DateStart Chambers Days/chm #Stations Weeks Technicians Engineer EndDate   Assume all UW unfinished are BW      
39 0.5 UM 24-Mar-04 60 8.0 3 31.8 6 2 02-Nov-04   And all UW in step 0.0 are unfinished      
40 0.5 UW 13-Mar-04 64 5.1 2 32.4 4 1 26-Oct-04              
41 0.5 BMC 09-May-04 76 3.6 2 27.7 2 1 19-Nov-04              
42             92.0 12 4                
43   Integration - Verification and Certification of CSC chambers with off-chamber electronics                
44                                  
45 0.5 Institution DateStart Chambers Days/chm #Stations Weeks Technicians Engineer EndDate              
46   BNL 01-Jan-05 32 3.0 1 19.2 2 1 15-May-05              
47                         CSC Hours CSC K$      
48   Hours of manpower above (tech only) = 19926 ~Cost in K$ 643 @ $20/hr with overhead and fringe benefits 1532 49      
49   Hours of manpower above (ProjEng) = 6880 ~Cost in K$ 444 @ $40/hr with overhead and fringe benefits 766 49      
50 ** Fraction of project hours (tech only) = 7605 ~Cost in K$ 245 @ $20/hr with overhead and fringe benefits 523 17      
51 ** Fraction of project hours (ProjEng only) = 2595 ~Cost in K$ 167 @ $40/hr with overhead and fringe benefits 262 17      
52   Fraction of M&O hours (tech only) = 12321 ~Cost in K$ 397 @ $20/hr with overhead and fringe benefits 1009 33      
53   Fraction of M&O hours (ProjEng only) = 4286 ~Cost in K$ 276 @ $40/hr with overhead and fringe benefits 505 33      
54                                  
55   Split total hours/time by WBS number                        
56       TechHrs EngHours K$                      
57   1.5.4.7   523 262 65     Total hours              
58   SW MDT   2257 1082 143     29105                
59   BW MDT   8074 2659 432                      
60   3.5.1.1.1.2.1   5343 1883 294                      
61   3.5.1.1.1.2.2   4236 1498 233                      
62   3.5.2.1.1.2.1   940 461 60                      
63   3.5.2.1.1.2.2   822 404 53                      
64   1.5.7.11.1   0 0 0   Remember, all unfinished were BW              
65   1.5.7.11.2   7605 2595 413                      
66   SW ALGN   451 187 27                      
67   BW ALGN   1538 506 82                      
68   3.5.3.1.2   1989 692 109                      
69                                  
70 1.0 Mount and verify chambers on big wheel C - Buffer sectors ready 4 months before lowering. N= 16            
71                                  
72   Institution DateStart Sectors Days/Sector #Stations Weeks Technicians PhD Engineers N SectorDate          
73   Composite 16-May-04 16 8 1 25.2 5 1 0.5 22-Mar-05 RFI          
74                                  
75 1.0 Mount and verify chambers on big wheel A - Buffer sectors ready 4 months before lowering. N= 16            
76                                  
77   Institution DateStart Sectors Days/Sector #Stations Weeks Technicians PhD Engineers N SectorDate          
78   Composite 02-Aug-04 16 8 1 25.2 5 1 0.5 08-Jun-05 RFI          
79                                  
80 1.5 Mount and verify chambers on big wheel C - Remainder of chambers                    
81                                  
82   Composite DateStart Sectors Days/Sector #Stations Weeks Technicians PhD Engineers Last Sector Commission          
83     22-Mar-05 0 8 1 0.0 5 1 0.5 22-Mar-05 10-Aug-06          
84                                  
85 1.5 Mount and verify chambers on big wheel A - Remainder of chambers                    
86                                  
87   Composite DateStart Sectors Days/Sector #Stations Weeks Technicians PhD Engineers Last Sector Commission          
88     08-Jun-05 0 8 1 0.0 5 1 0.5 08-Jun-05 10-Aug-06          
89                                  
90 2.0 Mount and verify chambers on small wheels - RFI is when wheel is ready to decend                
91                                  
92   Institution DateStart Wheels Days/wheel* #Stations Weeks Technicians PhD Engineers DateRFI Commission          
93   Composite 21-Apr-05 2 85 2 34.0 5 1 0.5 05-Jan-06 1-Jun-06          
94                                  
95 2.5 Mount EIL4 & EE chambers on frames - RFI is from Version 6                    
96                                  
97   Institution DateStart Frames Days/frame #Stations Weeks Technicians PhD Engineers DateRFI Commission          
98   Composite 27-May-04 4 16 2 12.8 4 1 0.5 15-Dec-04 1-Jun-06          
99                                  
100               Techs PhD Engineers Total            
101                           CSC part (included at left)  
102