ID

Task Name

Version 6

Version 5

Version 4

118

Feet and Bedplates Ready For Installation

4 Aug '03

21 Jul '03

15 Jun '03

119

Toroid Barrel Coil 1 Ready For Installation

15 Sep '03

4 Sep '03

15 Aug '03

120

HXT Structures Ready For Installation

30 Oct '03

17 Oct '03

31 Aug '03

127

Muon Barrel Rails Ready For Installation

17 Nov '03

NA

NA

128

Cryo ring Ready For Installation

9 Jan '04

NA

NA

123

Trucks (HF) Ready For Installation

20 Jan '04

5 Jan '04

15 Jan '04

124

Tile Barrel Ready For Installation

21 Jan '04

NA

15 Jan '04

121

Toroid Barrel Coil 8 Ready For Installation

2 Mar '04

16 Feb '04

31 Jan '04

125

LAr Barrel Ready For Installation

18 Mar '04

19 Mar '04

29 Feb '04

126

Chimney Ready For Installation

19 May '04

5 Jan '04

15 Apr '04

129

LAr Barrel FE-crates and electronics Ready For Installation

2 Jun '04

NA

NA

122

Shielding nose mono-blocks Ready For Installation

16 Jun '04

7 Jun '04

15 Apr '04

673

ID services from PP1 to PP2 & racks Ready For Installation

28 Jun '04

NA

NA

674

Tile Extended C Ready For Installation

5 Jul '04

14 Jul '04

15 Jun '04

675

LAr End-Cap C Ready For Installation

29 Jul '04

4 Aug '04

15 Jul '04

676

BIS chambers side A Ready for Installation

1 Sep '04

NA

NA

686

Muon Barrel Chambers side A Ready For Installation

1 Sep '04

2 Sep '04

31 Jul '04

687

Muon Barrel Chambers side C Ready For Installation

29 Oct '04

25 Oct '04

31 Oct '04

688

Tile Extended A Ready For Installation

21 Jan '05

7 Jan '05

31 Oct '04

689

LAr End-Cap A Ready For Installation

17 Feb '05

17 Feb '05

30 Nov '04

1096

Big Wheels side C Ready For Installation

22 Mar '05

1 Mar '05

15 Jan '05

690

Shield Discs Ready For Installation

20 May '05

14 Apr '05

31 Jan '05

1097

Inner Detector Barrel Ready For Installation

8 Jun '05

2 May '05

15 Feb '05

1099

Big Wheels side A Ready For Installation

8 Jun '05

3 Jun '05

15 Mar '05

1101

ID Inner End-Cap C Ready For Installation

1 Sep '05

28 Jul '05

15 May '05

1367

End-Cap Toroid C Ready For Installation

6 Sep '05

2 Aug '05

15 May '05

1370

Toroid Shielding Ready For Installation

14 Sep '05

10 Aug '05

31 Jul '05

1098

Shielding Nose washers Ready For Installation

21 Oct '05

12 Sep '05

15 May '05

1102

ID Inner End-Cap A Ready For Installation

1 Nov '05

14 Sep '05

15 Jun '05

1368

End-Cap Toroid A Ready For Installation

1 Nov '05

21 Sep '05

15 Jun '05

1103

Pixel integrated with VI Ready For Installation

2 Jan '06

14 Nov '05

15 May '05

1369

Fully instrumented Small Wheel C Ready For Installation

5 Jan '06

17 Nov '05

30 Jun '05

1371

Small Wheel A fully instrumented and Ready For Installation

23 Jan '06

12 Dec '05

15 Aug '04

1484

Toroid Beam Pipe Ready For Installation

13 Feb '06

27 Dec '05

31 Jul '05

1485

Shielding Beam Pipe Ready For Installation

16 Feb '06

30 Dec '05

31 Jul '05

1372

End wall chambers side C Ready For Installation

2 Mar '06

17 Jan '06

28 Dec '05

1373

End wall chambers side A Ready For Installation

2 Mar '06

3 Mar '06

1 Feb '06

1486

Forward Shielding Ready For Installation

23 Mar '06

17 Apr '06

30 Sep '05

Feet and Bedplates Ready For Installation

Toroid Barrel Coil 1 Ready For Installation

HXT Structures Ready For Installation

Muon Barrel Rails Ready For Installation

Cryo ring Ready For Installation

Trucks (HF) Ready For InstallationTile Barrel Ready For Installation

Toroid Barrel Coil 8 Ready For Installation

LAr Barrel Ready For Installation

Chimney Ready For Installation

LAr Barrel FE-crates and electronics Ready For Installation

Shielding nose mono-blocks Ready For Installation

ID services from PP1 to PP2 & racks Ready For Installation

Tile Extended C Ready For Installation

LAr End-Cap C Ready For InstallationBIS chambers side A Ready for Installation Muon Barrel Chambers side A Ready For Installation

Muon Barrel Chambers side C Ready For Installation

Tile Extended A Ready For Installation

LAr End-Cap A Ready For Installation

Big Wheels side C Ready For Installation

Shield Discs Ready For Installation

Inner Detector Barrel Ready For Install Big Wheels side A Ready For Installati

ID Inner End-Cap C Ready For In

End-Cap Toroid C Ready For Ins

Toroid Shielding Ready For Inst

Shielding Nose washers Read

ID Inner End-Cap A Ready Fo End-Cap Toroid A Ready For

Pixel integrated with VI R

Fully instrumented Small

Small Wheel A fully inst

Toroid Beam Pipe Rea

Shielding Beam Pipe

End wall chambers siEnd wall chambers si

Forward Shielding R

Qtr 4

Qtr 1

Qtr 2

Qtr 3

Qtr 4

Qtr 1

Qtr 2

Qtr 3

Qtr 4

Qtr 1

Qtr 2

Qtr 3

Qtr 4

Qtr 1

Qtr 2

Qtr 3

Qtr 4

Qtr 1

2003

2004

2005

2006

v.6 RFI Milestone

v.5 RFI Milestone

v.4 RFI Milestone

System actually ready

ATLAS INSTALLATION SCHEDULE v. 6.0

Ready For Installation Mi lestones

27 Sep '02

Page 1 /1

M. Kotamäki