118
Feet and Bedplates Ready For Installation
4 Aug '03
21 Jul '03
15 Jun '03
119
Toroid Barrel Coil 1 Ready For Installation
15 Sep '03
4 Sep '03
15 Aug '03
120
HXT Structures Ready For Installation
30 Oct '03
17 Oct '03
31 Aug '03
127
Muon Barrel Rails Ready For Installation
17 Nov '03
NA
NA
128
Cryo ring Ready For Installation
9 Jan '04
NA
NA
123
Trucks (HF) Ready For Installation
20 Jan '04
5 Jan '04
15 Jan '04
124
Tile Barrel Ready For Installation
21 Jan '04
NA
15 Jan '04
121
Toroid Barrel Coil 8 Ready For Installation
2 Mar '04
16 Feb '04
31 Jan '04
125
LAr Barrel Ready For Installation
18 Mar '04
19 Mar '04
29 Feb '04
126
Chimney Ready For Installation
19 May '04
5 Jan '04
15 Apr '04
129
LAr Barrel FE-crates and electronics Ready For Installation
2 Jun '04
NA
NA
122
Shielding nose mono-blocks Ready For Installation
16 Jun '04
7 Jun '04
15 Apr '04
673
ID services from PP1 to PP2 & racks Ready For Installation
28 Jun '04
NA
NA
674
Tile Extended C Ready For Installation
5 Jul '04
14 Jul '04
15 Jun '04
675
LAr End-Cap C Ready For Installation
29 Jul '04
4 Aug '04
15 Jul '04
676
BIS chambers side A Ready for Installation
1 Sep '04
NA
NA
686
Muon Barrel Chambers side A Ready For Installation
1 Sep '04
2 Sep '04
31 Jul '04
687
Muon Barrel Chambers side C Ready For Installation
29 Oct '04
25 Oct '04
31 Oct '04
688
Tile Extended A Ready For Installation
21 Jan '05
7 Jan '05
31 Oct '04
689
LAr End-Cap A Ready For Installation
17 Feb '05
17 Feb '05
30 Nov '04
1096
Big Wheels side C Ready For Installation
22 Mar '05
1 Mar '05
15 Jan '05
690
Shield Discs Ready For Installation
20 May '05
14 Apr '05
31 Jan '05
1097
Inner Detector Barrel Ready For Installation
8 Jun '05
2 May '05
15 Feb '05
1099
Big Wheels side A Ready For Installation
8 Jun '05
3 Jun '05
15 Mar '05
1101
ID Inner End-Cap C Ready For Installation
1 Sep '05
28 Jul '05
15 May '05
1367
End-Cap Toroid C Ready For Installation
6 Sep '05
2 Aug '05
15 May '05
1370
Toroid Shielding Ready For Installation
14 Sep '05
10 Aug '05
31 Jul '05
1098
Shielding Nose washers Ready For Installation
21 Oct '05
12 Sep '05
15 May '05
1102
ID Inner End-Cap A Ready For Installation
1 Nov '05
14 Sep '05
15 Jun '05
1368
End-Cap Toroid A Ready For Installation
1 Nov '05
21 Sep '05
15 Jun '05
1103
Pixel integrated with VI Ready For Installation
2 Jan '06
14 Nov '05
15 May '05
1369
Fully instrumented Small Wheel C Ready For Installation
5 Jan '06
17 Nov '05
30 Jun '05
1371
Small Wheel A fully instrumented and Ready For Installation
23 Jan '06
12 Dec '05
15 Aug '04
1484
Toroid Beam Pipe Ready For Installation
13 Feb '06
27 Dec '05
31 Jul '05
1485
Shielding Beam Pipe Ready For Installation
16 Feb '06
30 Dec '05
31 Jul '05
1372
End wall chambers side C Ready For Installation
2 Mar '06
17 Jan '06
28 Dec '05
1373
End wall chambers side A Ready For Installation
2 Mar '06
3 Mar '06
1 Feb '06
1486
Forward Shielding Ready For Installation
23 Mar '06
17 Apr '06
30 Sep '05
Feet and Bedplates Ready For Installation
Toroid Barrel Coil 1 Ready For Installation
HXT Structures Ready For Installation
Muon Barrel Rails Ready For Installation
Cryo ring Ready For Installation
Trucks (HF) Ready For InstallationTile Barrel Ready For Installation
Toroid Barrel Coil 8 Ready For Installation
LAr Barrel Ready For Installation
Chimney Ready For Installation
LAr Barrel FE-crates and electronics Ready For Installation
Shielding nose mono-blocks Ready For Installation
ID services from PP1 to PP2 & racks Ready For Installation
Tile Extended C Ready For Installation
LAr End-Cap C Ready For InstallationBIS chambers side A Ready for Installation Muon Barrel Chambers side A Ready For Installation
Muon Barrel Chambers side C Ready For Installation
Tile Extended A Ready For Installation
LAr End-Cap A Ready For Installation
Big Wheels side C Ready For Installation
Shield Discs Ready For Installation
Inner Detector Barrel Ready For Install Big Wheels side A Ready For Installati
ID Inner End-Cap C Ready For In
End-Cap Toroid C Ready For Ins
Toroid Shielding Ready For Inst
Shielding Nose washers Read
ID Inner End-Cap A Ready Fo End-Cap Toroid A Ready For
Pixel integrated with VI R
Fully instrumented Small
Small Wheel A fully inst
Toroid Beam Pipe Rea
Shielding Beam Pipe
End wall chambers siEnd wall chambers si
Forward Shielding R
Qtr 4
Qtr 1
Qtr 2
Qtr 3
Qtr 4
Qtr 1
Qtr 2
Qtr 3
Qtr 4
Qtr 1
Qtr 2
Qtr 3
Qtr 4
Qtr 1
Qtr 2
Qtr 3
Qtr 4
Qtr 1
2003
2004
2005
2006
v.6 RFI Milestone
v.5 RFI Milestone
v.4 RFI Milestone
System actually ready
ATLAS INSTALLATION SCHEDULE v. 6.0
Ready For Installation Mi lestones
27 Sep '02
Page 1 /1
M. Kotamäki