Bing Zhou US - ATLAS Muon meeting(Dec. 4, 2001)
The University of Michigan
EML3 Tooling Schedule
http:// ganesh .physics. lsa . umich . edu /~atlas/ems4/ems4.html
One of the reasons for EMS4 re -
tooling took 5 weeks:
-- We found both angle combs
had ‘bow’ (30 microns)
-- Understanding the bow, and
fixing them took one week.
Precision measurement and
survey must be done very
carefully, the iteration process
To setup combs need enough
time
UM EML3 re - tooling schedule:
Jan. 8 – Feb. 1 (4 weeks)
We will make our best effort to
Finish the re - tooling earlier
Bing Zhou US - ATLAS Muon meeting(Dec. 4, 2001)
The University of Michigan
EML3 Tooling Plan
Working plan for EML3 tooling
Goal: accuracy ~ 10 microns,
EML3 production start: Feb. 4, 2002
EMS4 tube assembly finish date: Dec. 17, 2001
Wiring station setup for EML3 series schedule:
Dec. 18 – Dec. 24, 2001
- Re - setup the tube production wiring station
- Re - setup the tube test stations
- Modify the wiring online control software
Bing Zhou US - ATLAS Muon meeting(Dec. 4, 2001)
The University of Michigan
EML3 Tooling Plan
Chamber assembly tooling work before
Christmas:
- Prepare the 14 deg. Combs (glue feet, survey
profile, attach vacuum bars)
- Re - build the EML3 (14 deg) stiff - back parts &
associate OPS/RASNIK system
- Re - setup the EML3 spacer frame assembly table
(100 microns flatness)
- Re - machine all the clamping bars
- Machine all the in - plane alignment parts
- Re - build the large 14 deg. Chamber carts (4)
- Re - build the gas - bar assembly station
Bing Zhou US - ATLAS Muon meeting(Dec. 4, 2001)
The University of Michigan
EML3 Tooling Plan
Re - setup the EML3 tooling (1/8/02 - 2/1/02)
- Final EMS4 comb survey (before dismount them)
- Granite table survey (tilt meter & BCAL)
- Assemble the stiffback frame (with 5 panels) and optics
on granite table
- OPS calibration on granite table
- Re - setup and align 9 combs on the granite table (4 angle
ones, 5 straight ones)
- Measure the alignment, and the comb heights
- Re - build the comb vacuum distribution system, and
perform the vacuum test
- Setup the sphere blocks on granite table
- Perform stiffback – sphere block test, take OPS
‘reference’ data for each layer
- Final precision measurements on combs and table
- Setup the PMO towers, and perform the calibrations
- Modify the GLUE, OPS, PMO, INPLAN software
- Dry run for EML3 assembly